DECOMMISSIONING OF GAS TURBINE & 3 AUXILIARIES FUEL OIL TANK

Bidding Offer end
RM 370,000.00

The Bidding will end in

Bidding EndedBidding Ended

MINIMUM BIDDING INCREMENT: RM5,000

You did not join the bidding!

DECOMMISSIONING OF GAS TURBINE & 3 AUXILIARIES FUEL OIL TANK

The work includes and not limited to the following:

  1. GT11 dismantling & removal: Perform work to dismantle, and to remove the whole set of decommissioned GT11 from Miri Power Station.

ii. Fuel Oil Tank (“FOT”) 2, 3 & 4 dismantle and removal:

  1. Perform work to dismantle, to remove and to transport out the decommissioned FOTs, connecting piping; including and not limited to dewatering, disposal of degraded diesel fuel, sludge and water, discard of contaminated soil, providing reports required by regulatory agencies, backfilling, replacing paving, walks, and landscaping, etc.


Our reference :
Model : Siemens SGT-500
Condition : Running Condition
Manufacturing Date :
Configuration sketch: